Bid Cobra

TxDOT Subcontracts for H4 CONSTRUCTION SERVICES, LLC

Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0443-02-023 KAUFMAN SH 198 08/07/2025 A. L. HELMCAMP, INC. 08/26 | 07/26 | 06/26 | 05/26 | 04/26 27.54% $1,491,624.58 42.00% $5,416,211.25
0176-08-026 ANGELINA FM 324 04/03/2025 A. L. HELMCAMP, INC. 08/26 | 07/26 | 06/26 | 05/26 | 04/26 0.28% $76,748.24 38.00% $27,410,085.59
1724-03-009 NAVARRO FM 2930 08/02/2023 A. L. HELMCAMP, INC. 08/26 | 07/26 | 06/26 | 05/26 | 04/26 0.95% $122,870.04 96.00% $12,933,688.64
0576-02-068 ANGELINA FM 58 05/05/2023 A. L. HELMCAMP, INC. 08/26 | 07/26 | 06/26 | 05/26 | 04/26 0.73% $67,613.28 99.00% $9,262,093.77
0519-02-019 HILL SH 174 05/05/2022 A. L. HELMCAMP, INC. 08/26 | 07/26 | 06/26 | 05/26 | 04/26 0.17% $38,820.11 99.00% $22,835,358.04