Bid Cobra

TxDOT Subcontracts for SKIDABRADER GROUP LLC

Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
6483-03-001 BEXAR IH0035 07/01/2025 ROY JORGENSEN ASSOCIATES, INC. 08/26 | 06/26 | 05/26 | 04/26 | 03/26 0.00% $0.00 52.00% $2,670,871.73
2398-01-057 TAYLOR SL 322 05/01/2025 TI-ZACK CONCRETE, LLC 08/26 | 07/26 | 06/26 | 05/26 | 04/26 0.56% $7,493.51 104.00% $1,338,126.80
0001-04-112 EL PASO US 85 05/01/2025 STRUCTURAL INTEGRITY GROUP LLC 08/26 | 07/26 | 06/26 | 05/26 | 04/26 1.61% $15,958.16 89.00% $991,189.90
1417-01-034 MONTGOMERY FM 1484 02/06/2025 DURWOOD GREENE CONSTRUCTION CO. 06/26 | 05/26 | 04/26 | 03/26 | 02/26 15.45% $1,326,140.41 108.00% $8,583,433.06
1062-03-053 MONTGOMERY FM 1485 01/07/2025 VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 13.29% $1,022,163.34 91.00% $7,691,221.50
0904-00-240 POTTER VARIOUS 01/07/2025 TI-ZACK CONCRETE, LLC 06/26 | 05/26 | 04/26 | 03/26 | 02/26 0.61% $7,790.41 103.00% $1,277,117.12
0047-06-177 COLLIN US 75 07/09/2024 O. TREVINO CONSTRUCTION, LLC 01/26 | 12/25 | 11/25 | 10/25 | 09/25 13.72% $429,499.81 93.00% $3,130,465.11
0028-13-135 JEFFERSON IH 10 05/02/2024 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 08/26 | 07/26 | 06/26 | 05/26 | 04/26 0.07% $380,670.98 37.00% $543,815,681.34
0046-01-070 RED RIVER BU 82-J 02/02/2024 AAD CONTRACTING INC. 08/26 | 07/26 | 06/26 | 05/26 | 04/26 1.02% $7,483.23 103.00% $733,650.17
0306-03-139 JEFFERSON SH 73 02/01/2024 SOUTHERN ROAD & BRIDGE, LLC 08/26 | 07/26 | 06/26 | 05/26 | 04/26 2.98% $350,369.51 99.00% $11,757,365.99
0008-12-094 TARRANT IH 20 05/04/2023 SELECT MAINTENANCE, L.L.C. 03/25 | 02/25 | 01/25 | 12/24 | 11/24 22.52% $1,508,779.97 96.00% $6,699,733.45
0508-02-132 CHAMBERS IH 10 06/01/2022 MAIN LANE INDUSTRIES LTD. 03/25 | 02/25 | 01/25 | 12/24 | 11/24 13.53% $300,519.45 105.00% $2,221,134.11
6386-68-001 BASTROP US0290 03/04/2022 TRP CONSTRUCTION GROUP, LLC 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.00% $0.00 36.00% $8,286,398.33
0739-02-140 JEFFERSON IH 10 03/03/2022 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 08/26 | 07/26 | 06/26 | 05/26 | 04/26 0.01% $31,554.27 54.00% $315,542,678.37
1690-01-134 LAMAR US 82 11/04/2021 HIGHWAY 19 CONSTRUCTION LLC 06/25 | 04/25 | 03/25 | 02/25 | 01/25 2.15% $64,372.43 100.00% $2,994,066.64