Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
3451-01-040 EL PASO FM 1281 06/27/2023 JORDAN FOSTER CONSTRUCTION, LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 5.99% $2,266,226.62 71.00% $37,833,499.45
0665-02-002 EL PASO SS 320 04/04/2023 JORDAN FOSTER CONSTRUCTION, LLC 08/25 | 07/25 | 06/25 | 05/25 | 04/25 4.96% $910,279.49 97.00% $18,352,409.05
2552-02-028 EL PASO SL 375 05/04/2022 JORDAN FOSTER CONSTRUCTION, LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 3.60% $5,130,138.24 85.00% $142,503,839.98
0374-02-097 EL PASO US 62 10/03/2018 JORDAN FOSTER CONSTRUCTION, LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 3.55% $9,624,400.97 90.00% $271,109,886.36