Show Job Controls
Bid Cobra

CAMERON BU 77X (0327-08-109)

Items: 16

County: CAMERON
Length: 0.0000 MILES (0.1672 MILES)
Highway: BU 77X
District: PHARR
Control Number: 0327-08-109
DBE Goal: 0.0%
Project: F 2026(907)
Guaranty: $4,000.00
Time: 81 WORKING DAYS
Engineer's Estimate: $224,192.00
Date: 08/05/2026 1:00 PM CDT (6 weeks ago) Changed
Contract Number: 8263245
Type: LANDSCAPE DEVELOPMENT
Project ID: A00191479
Contract Type: FEDERAL WAIVED
Project Description: LANDSCAPE IMPROVEMENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (6)
E
Engineer's Estimate
$224,192.00
$240,951.94
Over/Under Est: 7.48% $16,759.94
Over/Under Est: 16.11% $36,112.00
Amt Left: 8.03% $19,352.06
Over/Under Est: 21.45% $48,099.00
Amt Left: 13.01% $31,339.06
Delta: -4.61% -$11,987.00
Over/Under Est: 26.09% $58,496.00
Amt Left: 17.32% $41,736.06
Delta: -3.82% -$10,397.00
$338,028.00
Over/Under Est: 50.78% $113,836.00
Amt Left: 40.29% $97,076.06
Delta: -19.58% -$55,340.00
Over/Under Est: 300.82% $674,423.00
Amt Left: 272.94% $657,663.06
Delta: -165.84% -$560,587.00

Bid Items & Bid Tabulations

16 Total 0 of 16
CAMERON  |  BU 77X  |  PHARR  |  0327-08-109  |  08/05/2026 1:00 PM CDT  |  $224,192.00  |  F 2026(907)  |  LANDSCAPE DEVELOPMENT  |  81 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LUCANIA CONTRACTORS LLC
TEXAS ROAD CONSTRUCTION, LLC
TIGHT LINE CONSTRUCTION, LLC
GV LANDSCAPE AND CONSTRUCTION LLC
CASTILLO ARANDA LLC
CENTRAL NORTH CONSTRUCTION, LLC
EXCAV (SPECIAL)
CY 57.000 $200.000 $140.170 $200.000 $400.000 $120.000 $100.000 $500.000
EMBANK (FNL)(OC)(TY C)
CY 18.000 $50.000 $205.730 $150.000 $100.000 $90.000 $65.000 $1,500.000
BROADCAST SEED (PERM_URBAN_SAND)
SY 666.000 $10.000 $4.500 $5.000 $5.000 $3.000 $0.500 $10.000
IRRIGATION SYSTEM
LS 1.000 $20,000.000 $18,900.000 $80,000.000 $75,000.000 $70,000.000 $75,000.000 $250,000.000
PLANT SOIL MIX
CY 137.000 $50.000 $287.730 $40.000 $150.000 $90.000 $20.000 $125.000
PLANT BED PREP
SY 973.000 $10.000 $31.360 $20.000 $15.000 $5.000 $30.000 $20.000
LANDSCAPE EDGE
LF 1,140.000 $60.000 $39.010 $25.000 $45.000 $15.000 $22.000 $93.000
PLANT MATERIAL (1 GAL)
EA 383.000 $30.000 $90.720 $20.000 $12.000 $30.000 $105.000 $50.000
PLANT MATERIAL (5 GAL)
EA 173.000 $40.000 $65.520 $38.000 $40.000 $65.000 $200.000 $100.000
LANDSCAPE ESTABLISH
MO 9.000 $2,500.000 $1,134.000 $2,000.000 $2,000.000 $3,000.000 $2,500.000 $21,500.000
IRRIG SYS OPER AND MAINT
MO 9.000 $1,000.000 $1,638.000 $1,500.000 $1,000.000 $3,000.000 $5,000.000 $3,000.000
MOBILIZATION
LS 1.000 $21,342.000 $6,090.000 $50,000.000 $25,000.000 $45,000.000 $24,000.000 $125,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $2,076.940 $2,500.000 $2,500.000 $3,000.000 $4,500.000 $10,000.000
TMA (STATIONARY)
DAY 2.000 $800.000 $500.000 $300.000 $1,500.000 $12,000.000 $500.000 $1,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 300.000 $6.000 $11.250 $1.000 $10.000 $15.000 $20.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 300.000 $2.000 $3.600 $1.000 $3.000 $9.000 $10.000 $15.000
Totals: $224,192.000 $240,951.940 $260,304.000 $272,291.000 $282,688.000 $338,028.000 $898,615.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $10,000.00