Show Job Controls
Bid Cobra

CHAMBERS CR 398 (0920-39-033)

Items: 59

County: CHAMBERS
Length: 0.0800 MILES
Highway: CR 398
District: BEAUMONT
Control Number: 0920-39-033
DBE Goal: 0.0%
Project: BR 2024(647)
Guaranty: $29,000.00
Time: 222 WORKING DAYS
Engineer's Estimate: $1,431,058.00
Date: 08/06/2026 1:00 PM CDT (6 weeks ago) Changed
Contract Number: 8263035
Type: BRIDGE REPLACEMENT
Project ID: A00192187
Contract Type: FEDERAL
Project Description: LOUGHRIDGE DRIVE(CR 398) AT LEE GULLY-BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (6)
E
Engineer's Estimate
$1,431,058.00
$1,675,109.80
Over/Under Est: 17.05% $244,051.80
$1,744,267.01
Over/Under Est: 21.89% $313,209.01
Amt Left: 4.13% $69,157.21
Over/Under Est: 37.01% $529,637.26
Amt Left: 17.05% $285,585.46
Delta: -12.41% -$216,428.25
$2,049,867.30
Over/Under Est: 43.24% $618,809.30
Amt Left: 22.37% $374,757.50
Delta: -4.55% -$89,172.04
$2,137,900.16
Over/Under Est: 49.39% $706,842.16
Amt Left: 27.63% $462,790.36
Delta: -4.29% -$88,032.86
Over/Under Est: 79.82% $1,142,254.00
Amt Left: 53.62% $898,202.20
Delta: -20.37% -$435,411.84

Bid Items & Bid Tabulations

59 Total 0 of 59
CHAMBERS  |  CR 398  |  BEAUMONT  |  0920-39-033  |  08/06/2026 1:00 PM CDT  |  $1,431,058.00  |  BR 2024(647)  |  BRIDGE REPL  |  222 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CASTILLO ARANDA LLC
JFO SERVICES, LLC
ELITE CONTRACTORS AND EQUIPMENT LTD
MC2 CIVIL, LLC
ISI CONTRACTING, INC.
RAGLE CONSTRUCTION, INC.
PREPARING ROW
STA 4.700 $5,000.000 $15,000.000 $39,000.080 $20,000.000 $24,500.000 $12,000.000 $60,000.000
RMV (11") TRT/UNTRT BASE & ASPH PAV
SY 620.000 $10.000 $15.000 $16.320 $12.000 $20.000 $27.000 $25.000
EXCAV (ROADWAY)
CY 91.000 $15.000 $20.000 $13.950 $50.000 $50.000 $47.000 $500.000
EXCAV (CHANNEL)
CY 822.000 $20.000 $22.000 $31.620 $30.000 $45.000 $28.000 $50.000
EMBANK (FNL)(OC)(TY C)
CY 608.000 $35.000 $25.000 $23.500 $30.000 $25.000 $55.000 $75.000
EMBANK (FNL)(DC)(TY C)
CY 510.000 $40.000 $30.000 $31.050 $30.000 $45.000 $65.000 $75.000
FURN & PLACE TOPSOIL (4")
SY 980.000 $2.000 $10.000 $10.690 $5.000 $3.000 $10.000 $8.000
BROADCAST SEED (TEMP_WARM)
SY 540.000 $1.000 $0.500 $2.510 $2.000 $2.000 $3.600 $2.000
BROADCAST SEED (TEMP_COOL)
SY 540.000 $1.000 $0.500 $2.510 $2.000 $2.000 $3.600 $2.000
HYDRO MULCH SEED (PERM_RURAL_SANDY)
SY 1,080.000 $1.000 $0.500 $2.510 $2.000 $0.700 $2.330 $0.700
VEGETATIVE WATERING
TGL 5.570 $200.000 $90.000 $2,024.960 $18.000 $100.000 $218.000 $265.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 135.000 $130.000 $110.000 $314.780 $180.000 $250.000 $704.000 $173.000
PRIME COAT (AE-P)
GAL 139.000 $15.000 $10.000 $10.690 $15.000 $6.000 $48.500 $17.200
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 101.000 $350.000 $250.000 $729.370 $350.000 $230.000 $1,004.000 $400.000
TACK COAT
GAL 56.000 $10.000 $10.000 $9.430 $15.000 $10.000 $107.000 $22.000
PLANE & TEXT ASPH CONC PAV(2")
SY 215.000 $15.000 $55.000 $16.320 $10.000 $24.000 $18.000 $40.000
CEM STABIL BKFL
CY 48.000 $125.000 $105.000 $72.090 $215.000 $120.000 $180.000 $164.000
TEMPORARY SPL SHORING
SF 400.000 $50.000 $30.000 $50.300 $685.000 $50.000 $100.000 $156.000
PRESTR CONC PIL (16 IN SQ)
LF 360.000 $140.000 $310.000 $187.720 $150.000 $188.000 $625.000 $177.000
PRESTR CONC PIL (18 IN SQ)
LF 900.000 $125.000 $310.000 $165.250 $180.000 $210.000 $265.000 $146.000
CL C CONC (ABUT)
CY 18.400 $1,500.000 $1,350.000 $2,227.070 $2,000.000 $3,500.000 $2,700.000 $1,400.000
CL C CONC (CAP)
CY 19.800 $1,700.000 $1,450.000 $3,021.530 $2,850.000 $4,200.000 $3,300.000 $2,715.000
CL C CONC (RAIL FOUNDATION)
CY 2.500 $1,500.000 $675.000 $3,510.950 $600.000 $3,500.000 $1,798.000 $1,135.000
REINF CONC SLAB
SF 4,420.000 $20.000 $18.500 $30.580 $25.000 $41.000 $25.000 $26.000
APPROACH SLAB
CY 41.200 $800.000 $650.000 $747.780 $800.000 $1,000.000 $1,186.000 $642.000
PRESTR CONC SLAB BEAM (5SB15)
LF 840.000 $280.000 $320.000 $298.160 $300.000 $280.000 $260.000 $259.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 1,239.000 $185.000 $220.000 $73.280 $225.000 $260.000 $160.000 $262.000
RAIL (TY T223)
LF 382.000 $150.000 $140.000 $143.330 $180.000 $200.000 $170.000 $123.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 50.400 $180.000 $130.000 $421.990 $250.000 $210.000 $209.000 $220.500
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $50,000.000 $55,000.000 $32,343.770 $50,000.000 $50,000.000 $50,000.000 $305,000.000
MOBILIZATION
LS 1.000 $131,000.000 $100,000.000 $173,994.780 $160,000.000 $200,000.000 $150,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $5,000.000 $4,000.000 $2,655.300 $2,000.000 $5,500.000 $5,700.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 30.000 $50.000 $30.000 $50.300 $50.000 $55.000 $55.000 $40.530
ROCK FILTER DAMS (REMOVE)
LF 30.000 $20.000 $5.000 $37.720 $20.000 $12.000 $27.000 $12.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 111.000 $37.000 $35.000 $31.440 $40.000 $30.000 $27.000 $17.500
CONSTRUCTION EXITS (REMOVE)
SY 111.000 $15.000 $5.000 $12.570 $10.000 $15.000 $11.000 $15.400
TEMP SEDMT CONT FENCE (INSTALL)
LF 625.000 $6.000 $5.000 $3.770 $4.000 $5.000 $2.500 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 625.000 $2.000 $1.000 $1.880 $1.000 $1.000 $0.700 $0.990
CONSTRUCTING DETOURS
SY 286.000 $150.000 $40.000 $239.730 $150.000 $200.000 $360.000 $250.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 40.000 $80.000 $70.000 $154.500 $50.000 $145.000 $52.000 $150.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 80.000 $80.000 $70.000 $111.830 $50.000 $70.000 $52.000 $150.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 40.000 $25.000 $20.000 $49.900 $25.000 $30.000 $52.000 $30.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 80.000 $25.000 $20.000 $24.950 $25.000 $30.000 $52.000 $17.000
MTL W-BEAM GD FEN (TIM POST)
LF 37.500 $30.000 $40.000 $48.420 $40.000 $45.000 $44.000 $29.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $1,500.000 $1,950.000 $3,332.470 $2,000.000 $2,000.000 $2,134.000 $1,450.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,600.000 $2,000.000 $2,326.450 $2,000.000 $2,000.000 $2,012.000 $1,450.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,000.000 $3,820.000 $4,841.510 $3,800.000 $4,200.000 $4,194.000 $3,550.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 1.000 $25,000.000 $28,500.000 $34,393.560 $32,000.000 $25,000.000 $21,500.000 $26,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $500.000 $120.000 $861.410 $700.000 $110.000 $943.000 $931.000
REMOVE SM RD SN SUP&AM
EA 5.000 $85.000 $200.000 $251.510 $150.000 $200.000 $125.000 $120.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 4.000 $50.000 $30.000 $31.440 $50.000 $2.200 $31.800 $18.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 5.000 $50.000 $30.000 $44.010 $50.000 $9.000 $32.000 $25.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 2.000 $200.000 $315.000 $389.840 $500.000 $170.000 $329.000 $310.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $50.000 $50.000 $125.760 $50.000 $50.000 $37.000 $35.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 1,200.000 $2.000 $5.000 $1.260 $5.000 $3.500 $1.060 $1.000
PAVEMENT SLER 6"
LF 840.000 $1.000 $3.000 $0.630 $1.000 $0.500 $0.530 $0.500
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 940.000 $2.000 $3.000 $1.380 $6.000 $2.500 $1.170 $1.100
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 420.000 $2.000 $3.000 $1.380 $5.000 $2.500 $1.170 $1.100
PAV SURF PREP FOR MRK (6")
LF 1,360.000 $0.500 $1.000 $0.130 $1.000 $0.500 $0.110 $0.100
Totals: $1,431,058.000 $1,675,109.800 $1,744,266.992 $1,960,695.260 $2,049,867.300 $2,137,900.160 $2,573,312.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $10,000.00