PREPARING ROW
|
STA
|
7.700
|
$3,000.000
|
$92,000.000
|
$18,056.490
|
$100,000.000
|
|
|
|
REMOV CONC (RIPRAP)
|
SY
|
483.000
|
$20.000
|
$50.000
|
$21.260
|
$21.000
|
|
|
|
EXCAV (ROADWAY)
|
CY
|
1,485.000
|
$20.000
|
$20.000
|
$24.590
|
$15.750
|
|
|
|
EMBANK (FNL)(DC)(TY C2)
|
CY
|
1,423.000
|
$20.000
|
$30.000
|
$35.460
|
$63.000
|
|
|
|
EMBANK (FNL)(DC)(TY D)
|
CY
|
1,485.000
|
$20.000
|
$35.000
|
$8.030
|
$15.750
|
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
15,556.000
|
$5.000
|
$5.000
|
$1.870
|
$7.030
|
|
|
|
HYDRO MULCH SEED (PERM_URBAN_CLAY)
|
SY
|
15,556.000
|
$3.000
|
$2.000
|
$0.940
|
$0.910
|
|
|
|
HYDRO MULCH SEED (TEMP_WARM)
|
SY
|
3,889.000
|
$3.000
|
$1.000
|
$1.030
|
$1.000
|
|
|
|
HYDRO MULCH SEED (TEMP_COOL)
|
SY
|
3,889.000
|
$3.000
|
$1.000
|
$1.030
|
$1.000
|
|
|
|
VEGETATIVE WATERING
|
TGL
|
544.500
|
$30.000
|
$55.000
|
$55.000
|
$53.250
|
|
|
|
SOIL RET BLKT(SL_STEEP_CLAY_SHORT)
|
SY
|
761.000
|
$4.000
|
$5.000
|
$3.410
|
$3.300
|
|
|
|
SOIL RET BLKT(SL_STEEP_CLAY_LONG)
|
SY
|
1,186.000
|
$4.000
|
$6.500
|
$6.990
|
$6.760
|
|
|
|
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS)
|
CY
|
428.000
|
$60.000
|
$100.000
|
$113.210
|
$125.000
|
|
|
|
LIME (COM OR QK)(SLURRY)
|
TON
|
32.000
|
$350.000
|
$330.000
|
$348.810
|
$350.000
|
|
|
|
LIME TRT (EXIST MATL & NEW BASE)(8")
|
SY
|
1,927.000
|
$6.000
|
$12.000
|
$11.270
|
$10.000
|
|
|
|
SALV, HAUL & STKPL RCL APH PV (6 TO 8")
|
SY
|
1,850.000
|
$7.000
|
$12.000
|
$12.440
|
$10.630
|
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
353.000
|
$10.000
|
$26.000
|
$11.330
|
$19.170
|
|
|
|
D-GR HMA TY-B PG64-22 (EXEMPT)
|
TON
|
304.000
|
$180.000
|
$175.000
|
$227.150
|
$219.920
|
|
|
|
TACK COAT
|
GAL
|
381.000
|
$5.000
|
$25.000
|
$4.400
|
$4.260
|
|
|
|
SP MIXES SP-C SAC-A PG70-28
|
TON
|
199.000
|
$225.000
|
$235.000
|
$267.630
|
$259.110
|
|
|
|
CEM STABIL BKFL
|
CY
|
337.000
|
$220.000
|
$90.000
|
$126.110
|
$300.000
|
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
283.000
|
$11.000
|
$1.000
|
$1.450
|
$50.000
|
|
|
|
TEMPORARY SPL SHORING
|
SF
|
318.000
|
$35.000
|
$30.000
|
$44.000
|
$75.000
|
|
|
|
TEMPORARY SPL SHORING (COFFERDAM)
|
SF
|
1,082.000
|
$30.000
|
$50.000
|
$92.490
|
$75.000
|
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
142.000
|
$150.000
|
$270.000
|
$174.430
|
$170.000
|
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
711.000
|
$220.000
|
$400.000
|
$300.610
|
$275.000
|
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
74.400
|
$1,100.000
|
$1,300.000
|
$1,179.810
|
$1,500.000
|
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
52.200
|
$1,200.000
|
$1,450.000
|
$1,290.730
|
$1,600.000
|
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
13.500
|
$1,500.000
|
$1,200.000
|
$3,247.070
|
$2,500.000
|
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
19.000
|
$1,000.000
|
$750.000
|
$1,202.910
|
$750.000
|
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
12,482.000
|
$21.000
|
$25.000
|
$31.020
|
$30.000
|
|
|
|
APPROACH SLAB (HPC)
|
CY
|
98.200
|
$700.000
|
$650.000
|
$528.680
|
$1,000.000
|
|
|
|
PRESTR CONC GIRDER (TX46)
|
LF
|
1,754.640
|
$235.000
|
$280.000
|
$304.110
|
$300.000
|
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
1.000
|
$750.000
|
$550.000
|
$1,012.420
|
$2,100.000
|
|
|
|
RIPRAP (MOW STRIP)(5 IN)
|
CY
|
20.000
|
$870.000
|
$550.000
|
$639.830
|
$800.000
|
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
1,611.000
|
$150.000
|
$320.000
|
$218.160
|
$275.000
|
|
|
|
STR STEEL (MISC NON-BRIDGE)
|
LB
|
455.000
|
$60.000
|
$30.000
|
$22.260
|
$30.000
|
|
|
|
RAIL (TY C223)(HPC)
|
LF
|
747.900
|
$230.000
|
$135.000
|
$182.340
|
$200.000
|
|
|
|
RAIL (TY PR11)
|
LF
|
592.100
|
$155.000
|
$155.000
|
$119.270
|
$150.000
|
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
|
LF
|
117.000
|
$155.000
|
$150.000
|
$191.550
|
$200.000
|
|
|
|
CONC BOX CULV (6 FT X 4 FT)
|
LF
|
116.000
|
$650.000
|
$785.000
|
$669.490
|
$550.000
|
|
|
|
WINGWALL (FW - 0) (HW=9 FT)
|
EA
|
1.000
|
$25,000.000
|
$65,000.000
|
$18,209.150
|
$16,500.000
|
|
|
|
WINGWALL (SW - 0) (HW=6 FT)
|
EA
|
1.000
|
$12,000.000
|
$55,000.000
|
$13,829.940
|
$11,000.000
|
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$60,000.000
|
$25,000.000
|
$47,852.690
|
$100,000.000
|
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$400,000.000
|
$700,000.000
|
$906,007.690
|
$950,000.000
|
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
15.000
|
$7,000.000
|
$10,000.000
|
$6,156.120
|
$31,500.000
|
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
3.000
|
$8,000.000
|
$5,000.000
|
$20,212.500
|
$20,000.000
|
|
|
|
TMA (STATIONARY)
|
DAY
|
234.000
|
$200.000
|
$250.000
|
$272.580
|
$10.000
|
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
4.000
|
$250.000
|
$450.000
|
$1,322.330
|
$1,100.000
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
10.000
|
$110.000
|
$50.000
|
$165.000
|
$159.750
|
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
10.000
|
$15.000
|
$5.000
|
$60.500
|
$58.580
|
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
225.000
|
$25.000
|
$30.000
|
$54.290
|
$52.560
|
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
225.000
|
$10.000
|
$10.000
|
$24.200
|
$23.430
|
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,088.000
|
$5.000
|
$4.000
|
$3.410
|
$3.300
|
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,088.000
|
$1.500
|
$1.000
|
$1.490
|
$1.440
|
|
|
|
CONSTRUCTING DETOURS
|
SY
|
1,862.000
|
$100.000
|
$95.000
|
$77.770
|
$95.850
|
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
140.000
|
$80.000
|
$65.000
|
$118.520
|
$100.000
|
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$120.000
|
$65.000
|
$120.320
|
$200.000
|
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
140.000
|
$40.000
|
$20.000
|
$22.540
|
$50.000
|
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$15.000
|
$20.000
|
$23.640
|
$100.000
|
|
|
|
CONC SIDEWALKS (5")
|
SY
|
506.000
|
$100.000
|
$75.000
|
$64.300
|
$100.000
|
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
150.000
|
$25.000
|
$30.000
|
$27.500
|
$26.630
|
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
4.000
|
$1,300.000
|
$1,300.000
|
$1,320.000
|
$3,256.280
|
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,375.000
|
$1,300.000
|
$1,320.000
|
$1,278.000
|
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
609.000
|
$2.500
|
$10.000
|
$3.300
|
$3.200
|
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$3,300.000
|
$3,500.000
|
$3,300.000
|
$3,195.000
|
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$250.000
|
$300.000
|
$275.000
|
$266.250
|
|
|
|
WIRE FENCE (TY C)
|
LF
|
351.000
|
$30.000
|
$15.000
|
$15.590
|
$26.630
|
|
|
|
GATE (TY 1)
|
EA
|
1.000
|
$1,500.000
|
$2,500.000
|
$2,145.000
|
$2,662.500
|
|
|
|
WIRE FENCE (REMOVE)
|
LF
|
351.000
|
$3.000
|
$1.000
|
$3.030
|
$10.650
|
|
|
|
TEMP RD IL SETUP AND REMOVE
|
EA
|
2.000
|
$8,000.000
|
$15,000.000
|
$3,080.000
|
$16,000.000
|
|
|
|
TEMP RD IL MAINTAIN SYSTEM
|
MO
|
26.000
|
$400.000
|
$8,150.000
|
$1,045.000
|
$300.000
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
6.000
|
$825.000
|
$750.000
|
$819.500
|
$798.750
|
|
|
|
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
|
EA
|
2.000
|
$600.000
|
$500.000
|
$753.500
|
$559.130
|
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
1.000
|
$125.000
|
$350.000
|
$159.500
|
$159.750
|
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
|
EA
|
10.000
|
$22.000
|
$30.000
|
$22.000
|
$21.300
|
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
12.000
|
$27.500
|
$30.000
|
$27.500
|
$26.630
|
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)SRFLL(BI)
|
EA
|
2.000
|
$124.000
|
$100.000
|
$71.500
|
$69.230
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
1,415.000
|
$0.200
|
$2.000
|
$2.090
|
$1.500
|
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
1,400.000
|
$0.200
|
$2.000
|
$2.090
|
$1.500
|
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
298.000
|
$1.250
|
$5.000
|
$2.090
|
$6.000
|
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
323.000
|
$1.250
|
$5.000
|
$2.090
|
$6.000
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
200.000
|
$1.000
|
$20.000
|
$4.400
|
$5.000
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
200.000
|
$1.000
|
$20.000
|
$4.400
|
$5.000
|
|
|
|
WK ZN PAV MRK SHT TERM RMV (W)(4")
|
LF
|
1,540.000
|
$1.000
|
$5.000
|
$1.430
|
$6.000
|
|
|
|
WK ZN PAV MRK SHT TERM RMV (Y)(4")
|
LF
|
1,540.000
|
$1.000
|
$5.000
|
$1.430
|
$6.000
|
|
|
|
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
|
LF
|
2,164.000
|
$2.000
|
$2.000
|
$2.590
|
$1.500
|
|
|
|
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
|
LF
|
2,164.000
|
$2.000
|
$2.000
|
$2.590
|
$1.500
|
|
|
|
PAVEMENT SLER 6"
|
LF
|
4,328.000
|
$0.500
|
$1.000
|
$0.110
|
$0.550
|
|
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
27.000
|
$12.000
|
$15.000
|
$9.900
|
$10.000
|
|
|
|
ELIM EXT PM & MRKS (4")
|
LF
|
1,724.000
|
$1.000
|
$2.000
|
$2.420
|
$1.100
|
|
|
|
ELIM EXT PM & MRKRS (PLOWABLE RPMS)
|
EA
|
46.000
|
$1.000
|
$6.000
|
$5.500
|
$3.250
|
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
4,328.000
|
$0.600
|
$1.000
|
$0.110
|
$0.450
|
|
|
|
PAV SURF PREP FOR MRK (RPM)
|
EA
|
27.000
|
$2.000
|
$1.000
|
$0.110
|
$1.100
|
|
|
|
TIP TESTING(DRILL SHAFT)
|
EA
|
4.000
|
$22,000.000
|
$15,000.000
|
$4,510.000
|
$4,500.000
|
|
|
|
INSTALL FTB
|
LF
|
44.000
|
$50.000
|
$200.000
|
$186.840
|
$200.000
|
|
|
|
REMOVE FTB
|
LF
|
44.000
|
$4.000
|
$10.000
|
$88.000
|
$75.000
|
|
|
|
54" FRP GRAVITY SEWER PIPE, OPEN CUT
|
LF
|
982.000
|
$675.000
|
$1,400.000
|
$1,507.000
|
$1,459.050
|
|
|
|
5' DIA. VENTED DROP FRP MANHOLE
|
EA
|
1.000
|
$45,000.000
|
$25,400.000
|
$99,000.000
|
$95,850.000
|
|
|
|
5' DIA. VENTED FRP MANHOLE
|
EA
|
1.000
|
$40,000.000
|
$35,000.000
|
$93,500.000
|
$90,525.000
|
|
|
|
5' DIA. T-BASE FRP MANHOLE
|
EA
|
1.000
|
$40,000.000
|
$30,000.000
|
$88,000.000
|
$85,200.000
|
|
|
|
POINT OF ENTRY CONNECTION
|
LS
|
1.000
|
$25,000.000
|
$25,000.000
|
$49,500.000
|
$47,925.000
|
|
|
|
TIE-IN CONNECTIONS
|
LS
|
1.000
|
$35,000.000
|
$10,500.000
|
$44,000.000
|
$42,600.000
|
|
|
|
DECOMMISSION MANHOLE
|
EA
|
6.000
|
$5,000.000
|
$1,500.000
|
$4,400.000
|
$4,260.000
|
|
|
|
DECOMMISSION PIPES
|
LF
|
1,001.000
|
$100.000
|
$50.000
|
$330.000
|
$319.500
|
|
|
|
DEWATRING AND GROUNDWATER CONTROL
|
LS
|
1.000
|
$35,000.000
|
$35,000.000
|
$82,500.000
|
$79,875.000
|
|
|
|
TEMPORARY COFFERDAM AND FLOW DIVERSION
|
LS
|
1.000
|
$150,000.000
|
$3,000.000
|
$137,500.000
|
$133,125.000
|
|
|
|
TRENCH SAFETY
|
LF
|
982.000
|
$25.000
|
$10.000
|
$22.000
|
$21.300
|
|
|
|
STORM WATER POLLUTION PREVENTION PLAN
|
LS
|
1.000
|
$10,000.000
|
$50,000.000
|
$19,800.000
|
$19,561.230
|
|
|
|
BANK STABILIZATION
|
CY
|
2,543.000
|
$100.000
|
$12.000
|
$279.400
|
$391.920
|
|
|
|
HYDROMULCH
|
AC
|
1.000
|
$6,000.000
|
$3,000.000
|
$4,620.000
|
$41,013.150
|
|
|
|
WATERLINE SUPPORT
|
EA
|
2.000
|
$20,000.000
|
$4,500.000
|
$5,500.000
|
$5,325.000
|
|
|
|
PAVEMENT RESTORATION
|
LF
|
90.000
|
$750.000
|
$200.000
|
$605.000
|
$585.750
|
|
1
|
|
TEMPORARY BYPASS PUMPING
|
LS
|
1.000
|
$60,000.000
|
$0.000
|
$621,500.000
|
$601,725.000
|
|
1A
|
|
FLOW ISOLATION AND BYPASS PUMPING
|
LS
|
1.000
|
$60,000.000
|
$65,000.000
|
$0.000
|
$0.000
|
|
Totals: |
$5,147,705.450
|
$7,071,177.700
|
$8,292,005.167
|
$9,967,742.905
|