Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0076-07-037 UPTON US 67 10/08/2025 JONES BROS. DIRT & PAVING CONTRACTORS, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.40% $105,064.43 16.00% $26,266,106.66
0327-03-050 KENEDY US 77 04/04/2025 FOREMOST PAVING, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.16% $98,572.64 29.00% $61,607,900.27
0139-08-040 PECOS US 285 04/03/2025 JONES BROS. DIRT & PAVING CONTRACTORS, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.39% $104,748.15 18.00% $26,858,499.32
0076-07-040 UPTON US 67 01/08/2025 JONES BROS. DIRT & PAVING CONTRACTORS, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.46% $61,074.79 90.00% $13,277,128.50
0327-04-039 KENEDY US 77 08/02/2024 FOREMOST PAVING, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.20% $186,164.05 34.00% $93,082,026.74
0327-04-037 KENEDY US 77 08/01/2024 FOREMOST PAVING, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.14% $46,911.74 40.00% $33,508,385.70
2952-01-009 HARDIN FM 2937 06/05/2024 TEXAS MATERIALS GROUP, INC. 09/25 | 08/25 | 07/25 | 06/25 | 05/25 2.24% $189,089.00 93.00% $8,441,473.15
0271-01-083 COLORADO IH 10 05/03/2024 PULICE CONSTRUCTION, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.03% $122,707.68 53.00% $409,025,591.98
0920-03-082 HARDIN CR 05/03/2024 TEXAS MATERIALS GROUP, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.18% $7,094.01 98.00% $3,941,118.79
1109-01-026 JASPER FM 777 04/05/2024 TEXAS MATERIALS GROUP, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 4.89% $513,712.18 90.00% $10,505,361.59
0089-07-154 WHARTON US 59 12/06/2023 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.02% $68,541.51 23.00% $342,707,534.92
0200-08-049 TYLER US 69 09/06/2023 PULICE CONSTRUCTION, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.55% $1,228,080.60 70.00% $223,287,381.00
0389-07-025 GALVESTON SH 146 04/04/2023 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.01% $9,055.38 23.00% $90,553,802.33
0178-09-018 HARRIS SH 35 03/07/2023 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.04% $38,767.26 94.00% $96,918,145.25
0076-06-037 UPTON US 67 09/07/2022 JONES BROS. DIRT & PAVING CONTRACTORS, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.03% $8,485.48 89.00% $28,284,940.63
0522-04-032 SMITH FM 16 08/03/2022 HIGHWAY 19 CONSTRUCTION LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.38% $173,305.34 87.00% $45,606,668.62
0739-02-140 JEFFERSON IH 10 03/03/2022 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.05% $157,732.50 53.00% $315,464,992.12
0228-04-043 ANDREWS US 385 01/07/2022 REECE ALBERT, INC. 10/24 | 09/24 | 08/24 | 07/24 | 06/24 0.28% $105,399.85 96.00% $37,642,802.47
0200-16-020 JEFFERSON US 69 09/02/2021 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.02% $16,316.54 80.00% $81,582,703.12
0675-07-097 WALKER IH 45 09/02/2021 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.02% $43,857.20 73.00% $219,286,002.44
1685-03-098 HARRIS FM 1960 09/04/2020 WEBBER, LLC 02/26 | 01/26 | 12/25 | 11/25 | 10/25 0.23% $173,996.57 107.00% $75,650,682.87
0028-14-091 ORANGE IH 10 06/05/2020 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.01% $5,836.02 98.00% $58,360,157.27
0089-08-098 WHARTON US 59 01/10/2020 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.00% $0.00 100.00% $177,981,571.43
0500-04-106 GALVESTON IH 45 06/05/2018 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.01% $24,972.74 82.00% $249,727,443.11