Bid Cobra

TxDOT Subcontracts for TRUE ROADS CONSTRUCTION LLC

Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0546-01-040 TITUS FM 71 10/09/2025 THK CONSTRUCTION LLC 06/26 | 05/26 | 04/26 | 03/26 | 02/26 10.64% $141,674.30 99.00% $1,331,525.42
0553-03-034 NACOGDOCHES SH 7 05/01/2025 THK CONSTRUCTION LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 12.80% $799,860.61 94.00% $6,248,910.99
0610-03-104 TITUS IH 30 09/06/2024 THK CONSTRUCTION LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 2.22% $166,429.03 104.00% $7,496,803.10
0191-01-094 SMITH US 69 02/02/2023 DREWERY CONSTRUCTION COMPANY, INCORPORATED 07/26 | 06/26 | 05/26 | 04/26 | 03/26 2.35% $184,509.90 96.00% $7,851,485.13